5. Timelines and internal procedures
We will make a decision on the application within 120 days after we consider the documentation package to be complete.
The applicant will be given the opportunity to submit missing documentation after
- the completeness check (CC)
- the assessment of the ecotox and e-fate group
- the assessment of the remaining groups
The applicant will have 3 weeks after each of these steps to submit the requested information. The application will be rejected if it is found to be incomplete after these three steps.
See examples of frequent deficiencies
Procedural steps of the assessment of mutual recognitions in Norway:
| Procedure |
1. | Application may be pre-notified |
2. | Application received |
3. | Completeness check |
4. | The NFSA orders an agronomical assessment from NIBIO |
5. | The e-fate and ecotox groups assess the documentation |
6. | In case of denial based on environmental concerns: In case of approval: |
7. | The mammalian tox, residues and phys-chem groups assess the documentation |
8. | The decision is finalised and sent to the applicant |
9. | The product label is approved and given a registration number |
10. | The label with registration number is published on the NFSA website |